How to handle change orders on a landscaping job in Armstrong, BC

Updated 2026-11-15

A change order is a written note that changes the scope, price, or schedule of a job after the contract is signed. On a landscaping job in Armstrong, some change is normal. The ground hides things. Weather shifts. You see the space take shape and want something different. The goal is not to avoid every change. It is to write each one down before the work happens, so the final bill matches what you agreed to.

Why scope changes mid-job

Most changes come from one of these sources.

What the ground hides. Buried concrete, old footings, large rocks, a forgotten septic tank, or a layer of hard clay can appear when the digging starts. Each one adds time and haul-away. Soil varies lot to lot here, and many yards have heavy or compacted soil below the topsoil.

Utility lines. The BC 811 locate marks public utilities. It does not mark private lines, such as the wire to a shed or an old irrigation main. A crew that finds one has to work around it.

Water. A spot that stays wet after the first rain of the job may need a drain the plan did not include.

Materials. A paver color or a plant may be out of stock. The substitute may cost more or less.

Your own choices. You see the patio laid out and want it wider. You decide to add lighting while the trench is open. These are good reasons to change. They still need a change order.

Weather. A late thaw or an early freeze can push work into another season. That is a schedule change, and it belongs in writing too.

What a change order includes

A change order can be short. It needs five things:

  • What is changing, in plain words
  • Why it is changing
  • The change in price, up or down
  • The change in schedule, if any
  • Both signatures, or a clear written “yes” from both sides

A text message with a photo and a price can serve as a change order in the moment, as long as both sides reply with agreement. Follow it up with a one-page form or an email that repeats the terms. Keep all of it.

How to document a change fast

Crews cannot wait long. If they hit rock on Tuesday morning, they need an answer by Tuesday afternoon. A good process looks like this:

  1. The contractor stops work on that part and calls or texts you with a photo.
  2. The contractor gives you options and a price for each.
  3. You pick one and reply in writing.
  4. The contractor sends a short change order that night.
  5. You sign or reply “agreed” the next morning.

Agree on this process before the job starts. Put it in the contract. Name who on the crew can propose a change and who in your household can approve one.

How to keep costs from creeping

Change orders are where many jobs go over budget. These habits keep them in check.

Set an allowance for unknowns. Before the job, ask the contractor what could go wrong below ground and what it might cost. Set that money aside. If it is not needed, you keep it.

Get unit prices up front. Ask for the price of one more square meter of pavers, one more meter of wall, one more shrub, or one more hour of machine time. With unit prices in the contract, a change order is math, not a new negotiation.

Ask for a stop point. For any change, ask the crew to stop and show you before the extra work goes further. A photo of the problem with a tape measure in the shot is enough.

Bundle small changes. Many small additions add up. Ask the contractor to hold minor changes and present them together once a week, so you can see the running total.

Say no. You can decline a change. If the contractor hits rock under a planned bed, you can move the bed instead of paying to remove the rock.

Ask what is cheaper now. A change that adds work on day two is cheaper than the same change on day ten, after the base is in. If you are thinking about adding something, say so early.

Changes you ask for and changes the contractor asks for

When you ask for a change, expect to pay for the extra work and any materials. Expect the schedule to move too.

When the contractor asks for a change, ask why. Some reasons are fair: hidden conditions, out-of-stock materials, a safety issue. Some are not. If the contractor measured wrong, ordered the wrong color, or missed something they could have seen at the site visit, that is a mistake, not a change. The cost belongs to them.

The line is not always clear. A calm conversation about what the contract said and what the site visit showed settles most cases. Your written scope is the reference. The guide to what a landscaping quote should include explains why a detailed scope matters so much here.

Watch for scope creep from both sides

Scope creep is when the job grows a little at a time, with no clear decision. The crew adds a few more pavers to square off an edge. You ask them to move a shrub while they are there. Nobody writes it down. At the end, the bill is higher and nobody can say why.

The fix is simple. Any work not in the contract gets a change order, even a small one. Even a change with no cost gets a note, so the record is complete.

Keep a running log

Keep one document, on paper or on your phone, with every change in order. For each one, note the date, what changed, the cost, and the new total. Update it the same day.

Before each progress payment, compare the log to the invoice. The invoice needs to match the original price plus the signed changes. If it does not, ask before you pay. The guide to deposits and progress payments covers how payments and changes fit together.

What to do next

Before you sign the contract, add a change order clause. It names the process, the unit prices, and who can approve. During the job, hold to it. If the job is large or has unknowns below ground, a design with a site assessment reduces surprises. See landscape design for what that involves.